| Project Name | Guided Tour Project |
| Scenario Name | West Swathes Only |
| Vessel Name | M.V survOPT Pre-Release |
| Start Of Mobilization | 1/01/2008 |
| Start Of Production | 1/01/2008 |
| Vessel Time | 6/01/2008 10:36:00 PM |
| Client Name | Client |
| Area Name | Area |
| Comment | Lines on the Eastern half of the survey have been set "not required" and we are looking for a smart way to shoot just the westerly section |
| Equipment Configuration | |
| Streamers | 6 |
| Sources | 1 |
| Separation | 100 |
| Streamer Spread | 500 |
| Extra Spread (m) | 100 |
| Total Spread (m) | 600 |
| Streamer Length (m) | 6000 |
| Total Length (m) | 6500 |
| Performance | |
| Turn Radius (m) | 3000 |
| Online Speed (knots) | 4.00 |
| Offline Speed (knots) | 4.00 |
| Turning Speed (knots) | 3.50 |
| Safe Draft (m) | 20 |
| Contract | |
| Run In (m) | 6000 |
| Run Out (m) | 3000 |
| Max Missed Shots | 8 |
| Line Change Limit | 8:00 |
| Configuration Statistics | |
| Expected Shot Interval (s) | 12.1 |
| Min Circle Duration | 4:32 |
| Min Normal Line Change | 2:40 |
| Infill Rate | 20.00 % |
| Infill Efficiency | 100.00 % |
| Downtime Rate | 10.00 % |
| Standby Rate | 10.00 % |
| Circular Objects | 4 |
| Polygonal Objects | 0 |
| Preplots | 114 |
| Heading(s) | 195.9 |
| SPI (m) | 25.00 |
| Total Length (km) | 2678.89 (not including runouts) |
| Average Length (km) | 23.50 |
| Spacing (m) | 200 |
| Area (Sq. km) | 535.8 (avg length x spacing x preplots) |
| Type | Total | Average Length (km) | Total Length (km) | % Length Total |
| All | 47 | 17.95 | 843.66 | — |
| Prime | 45 | 18.53 | 834.03 | 98.86 % |
| Infill | 2 | 4.81 | 9.62 | 1.14 % |
| Reshoot | 0 | 0.00 | 0.00 | 0.00 % |
| Type | Total | Average Length (km) | Total Length (km) | % Length Total |
| All | 28 | 19.74 | 552.79 | — |
| Prime | 27 | 20.03 | 540.77 | 97.82 % |
| Infill | 0 | 0.00 | 0.00 | 0.00 % |
| Reshoot | 1 | 12.03 | 12.03 | 2.18 % |
| (DNP) | 1 | 12.03 | 12.03 | 0.00 % |
| % Complete | 39.6 % |
| % Prime Complete | 39.3 % |
| % Prime Incomplete | 60.7 % |
| % Complete Infill | 0.0 % |
| % Required Infill | 0.7 % |
| % Undershoot | 12.7 % |
| Undershoots | 39 |
| Total Length on Preplots (m) | 230391 |
| Avg Length on Preplot (m) | 8707.16 |
| Total Obstructed Shots | 9217 |
| Avg Obstructed Shots | 236.33 |
| Minimum Production Duration | 9d 21:28 |
| Expected Infill | 1d 22:46 |
| Expected Downtime | 1d 11:32 |
| Expected Standby | 1d 11:32 |
| Expected Duration | 14d 19:17 |
| Expected Demob | 0:00 |
| Current Vessel Time | 1/01/2008 |
| Minimum Completion Time | 16/01/2008 8:03:52 PM |
| Expected Completion Time | 21/01/2008 5:53:21 PM |
| Expected End of Demob | 21/01/2008 5:53:21 PM |
| Total Cost Estimate ($2,664,669) | |||
| Total Cost Estimate | $2,664,669 | ||
| Avg Total Cost Per FF Prime Km | 711.48 km | $3,745 | |
| Avg Total Cost Per FF Sq Km | 142.30 sq km | $18,726 | |
| Distance and Area Based Costs - N/A | |||
| Production Duration Costs (14d 19:17) $2,664,669 | |||
| Online | Duration | Rate | Cost |
| Recording Prime | 4d 13:21 | $200,000 | $911,252 |
| Infill Estimate Online | 21:52 | $200,000 | $182,250 |
| Recording Infill | 1:18 | $200,000 | $10,824 |
| Subtotal | 5d 12:31 | $1,104,327 | |
| Offline | Duration | Rate | Cost |
| Line Change Prime | 5d 04:29 | $200,000 | $1,037,370 |
| Infill Estimate Offline | 1d 00:54 | $200,000 | $207,474 |
| Line Change Infill | 2:20 | $200,000 | $19,424 |
| Downtime Estimate | 1d 11:32 | — | — |
| Standby Estimate | 1d 11:32 | $200,000 | $296,074 |
| Subtotal | 9d 06:46 | $1,560,342 | |
| Shot Based Costs - N/A | |||
| Mobilization Costs - N/A | |||
| Demobilization Costs - N/A | |||
| Completion Estimates | |||
| Minimum | Expected | ||
| Normal Priority | 16/01/2008 20:03 | 21/01/2008 17:52 | |
| End Production | 16/01/2008 20:03 | 21/01/2008 17:53 | |
| End Demob | 16/01/2008 20:03 | 21/01/2008 17:53 | |
| General | |||
| Online Duration | 4d 14:39 | ||
| Offline Duration | 5d 06:49 | ||
| Overall Duration | 9d 21:28 | ||
| All Sequences | |||
| Total Sequences | 47 | ||
| Total Duration | 4d 14:39 | ||
| Average Duration | 2:21 | ||
| Total Distance | 819.73 km | ||
| Average Distance | 17.44 km | ||
| All Line Changes | |||
| Total LCs | 47 | ||
| Total LC Expected | 5d 05:28 | ||
| Total LC Delays | 1:21 | ||
| Total LC Duration | 5d 06:49 | ||
| Average LC Duration | 2:42 | ||
| Standard Turn Duration | 2:40 | ||
| Obstructed LCs | 0 | ||
| Calibrated Line Changes | |||
| Calibrated LC's | 47 | ||
| Calibrated LC Duration | 2:42 | ||
| Calibrated LC Error | 0:02 | ||
| Sequence by Type | |||
| # | Average | Total | |
| Prime | 45 | 2:26 | 4d 13:21 |
| Infill | 2 | 0:39 | 1:18 |
| Reshoot | 0 | 0:00 | 0:00 |
| DNP | 0 | 0:00 | 0:00 |
| Line Changes by Type | |||
| # | Average | Total | |
| To Prime | 45 | 2:46 | 5d 04:29 |
| To Infill | 2 | 1:10 | 2:20 |
| To Reshoot | 0 | 0:00 | 0:00 |
| To DNP | 0 | 0:00 | 0:00 |
| Mobilization Duration | 0:00 |
| Production Duration | 0:00 |
| Start of Mobilization | 1/01/2008 |
| Start of Production | 1/01/2008 |
| Start of First Sequence | 1/01/2008 |
| End of Last Sequence | 6/01/2008 10:36:00 PM |
| Total Cost Estimate ($1,188,333) | |||
| Total Cost Estimate | $1,188,333 | ||
| Avg Total Cost Per FF Prime Km | 472.04 km | $2,517 | |
| Avg Total Cost Per FF Sq Km | 94.41 sq km | $12,587 | |
| Distance and Area Based Costs - N/A | |||
| Production Duration Costs (5d 22:36) $1,188,333 | |||
| Online | Duration | Rate | Cost |
| Recording Prime | 3d 01:42 | $200,000 | $614,167 |
| Recording Reshoot | 3:41 | $200,000 | $30,694 |
| Recording DNP | 1:37 | $200,000 | $13,472 |
| Subtotal | 3d 07:00 | $658,333 | |
| Offline | Duration | Rate | Cost |
| Line Change Prime | 2d 10:14 | $200,000 | $485,278 |
| Line Change Reshoot | 2:41 | $200,000 | $22,361 |
| Line Change DNP | 2:41 | $200,000 | $22,361 |
| Subtotal | 2d 15:36 | $530,000 | |
| Shot Based Costs - N/A | |||
| Mobilization Costs - N/A | |||
| Demobilization Costs - N/A | |||
| General | |||
| Online Duration | 3d 07:00 | ||
| Offline Duration | 2d 15:36 | ||
| Overall Duration | 5d 22:36 | ||
| All Sequences | |||
| Total Sequences | 29 | ||
| Total Duration | 3d 07:00 | ||
| Average Duration | 2:43 | ||
| Total Distance | 564.82 km | ||
| Average Distance | 19.48 km | ||
| All Line Changes | |||
| Total LCs | 29 | ||
| Total LC Expected | 2d 18:16 | ||
| Total LC Delays | -2:40 | ||
| Total LC Duration | 2d 15:36 | ||
| Average LC Duration | 2:16 | ||
| Standard Turn Duration | 2:40 | ||
| Obstructed LCs | 0 | ||
| Calibrated Line Changes | |||
| Calibrated LC's | 28 | ||
| Calibrated LC Duration | 2:16 | ||
| Calibrated LC Error | 0:07 | ||
| Sequence by Type | |||
| # | Average | Total | |
| Prime | 27 | 2:44 | 3d 01:42 |
| Infill | 0 | 0:00 | 0:00 |
| Reshoot | 1 | 3:41 | 3:41 |
| DNP | 1 | 1:37 | 1:37 |
| Line Changes by Type | |||
| # | Average | Total | |
| To Prime | 27 | 2:09 | 2d 10:14 |
| To Infill | 0 | 0:00 | 0:00 |
| To Reshoot | 1 | 2:41 | 2:41 |
| To DNP | 1 | 2:41 | 2:41 |