Guided Tour Project
West Swathes Only


General Information

Project NameGuided Tour Project
Scenario NameWest Swathes Only
Vessel NameM.V survOPT Pre-Release
Start Of Mobilization1/01/2008
Start Of Production1/01/2008
Vessel Time6/01/2008 10:36:00 PM
Client NameClient
Area NameArea
CommentLines on the Eastern half of the survey have been set "not required" and we are looking for a smart way to shoot just the westerly section

Acquisition Configuration

Equipment Configuration
Streamers6
Sources1
Separation100
Streamer Spread500
Extra Spread (m)100
Total Spread (m)600
Streamer Length (m)6000
Total Length (m)6500
Performance
Turn Radius (m)3000
Online Speed (knots)4.00
Offline Speed (knots)4.00
Turning Speed (knots)3.50
Safe Draft (m)20
Contract
Run In (m)6000
Run Out (m)3000
Max Missed Shots8
Line Change Limit8:00
Configuration Statistics
Expected Shot Interval (s)12.1
Min Circle Duration4:32
Min Normal Line Change2:40

Basic Allowances

Infill Rate20.00 %
Infill Efficiency 100.00 %
Downtime Rate10.00 %
Standby Rate10.00 %

Objects

Circular Objects4
Polygonal Objects0
preplots, objects & incomplete lines

Preplots

Preplots114
Heading(s)195.9
SPI (m)25.00
Total Length (km)2678.89 (not including runouts)
Average Length (km)23.50
Spacing (m)200
Area (Sq. km)535.8 (avg length x spacing x preplots)

Incomplete Lines

TypeTotalAverage Length (km)Total Length (km)% Length Total
All4717.95843.66
Prime4518.53834.0398.86 %
Infill24.819.621.14 %
Reshoot00.000.000.00 %

Completed Lines

TypeTotalAverage Length (km)Total Length (km)% Length Total
All2819.74552.79
Prime2720.03540.7797.82 %
Infill00.000.000.00 %
Reshoot112.0312.032.18 %
(DNP)112.0312.030.00 %

Useful Numbers

% Complete39.6 %
% Prime Complete39.3 %
% Prime Incomplete60.7 %
% Complete Infill0.0 %
% Required Infill0.7 %
% Undershoot12.7 %

Undershoots

Undershoots39
Total Length on Preplots (m)230391
Avg Length on Preplot (m)8707.16
Total Obstructed Shots9217
Avg Obstructed Shots236.33

Planned Production

Selected Search Result


shooting plan

Durations

Minimum Production Duration9d 21:28
Expected Infill1d 22:46
Expected Downtime1d 11:32
Expected Standby1d 11:32
Expected Duration14d 19:17
Expected Demob0:00

Dates

Current Vessel Time1/01/2008
Minimum Completion Time16/01/2008 8:03:52 PM
Expected Completion Time21/01/2008 5:53:21 PM
Expected End of Demob21/01/2008 5:53:21 PM

Planned Production

Costing Report

Total Cost Estimate ($2,664,669)
Total Cost Estimate$2,664,669
Avg Total Cost Per FF Prime Km711.48 km$3,745
Avg Total Cost Per FF Sq Km142.30 sq km$18,726
 
Distance and Area Based Costs - N/A
Production Duration Costs (14d 19:17) $2,664,669
OnlineDurationRateCost
Recording Prime4d 13:21$200,000$911,252
Infill Estimate Online21:52$200,000$182,250
Recording Infill1:18$200,000$10,824
Subtotal5d 12:31$1,104,327
 
OfflineDurationRateCost
Line Change Prime5d 04:29$200,000$1,037,370
Infill Estimate Offline1d 00:54$200,000$207,474
Line Change Infill2:20$200,000$19,424
Downtime Estimate1d 11:32
Standby Estimate1d 11:32$200,000$296,074
Subtotal9d 06:46$1,560,342
 
Shot Based Costs - N/A
Mobilization Costs - N/A
Demobilization Costs - N/A
Completion Estimates
MinimumExpected
Normal Priority16/01/2008 20:0321/01/2008 17:52
End Production16/01/2008 20:0321/01/2008 17:53
End Demob16/01/2008 20:0321/01/2008 17:53

Production Statistics

General
Online Duration4d 14:39
Offline Duration5d 06:49
Overall Duration9d 21:28
 
All Sequences
Total Sequences47
Total Duration4d 14:39
Average Duration2:21
Total Distance819.73 km
Average Distance17.44 km
 
All Line Changes
Total LCs47
Total LC Expected5d 05:28
Total LC Delays1:21
Total LC Duration5d 06:49
Average LC Duration2:42
Standard Turn Duration2:40
Obstructed LCs0
 
Calibrated Line Changes
Calibrated LC's47
Calibrated LC Duration2:42
Calibrated LC Error0:02
 
Sequence by Type
#AverageTotal
Prime452:264d 13:21
Infill20:391:18
Reshoot00:000:00
DNP00:000:00
 
Line Changes by Type
#AverageTotal
To Prime452:465d 04:29
To Infill21:102:20
To Reshoot00:000:00
To DNP00:000:00
 

Completed Production

Sequences Already Acquired

shooting plan

Durations

Mobilization Duration0:00
Production Duration0:00

Dates

Start of Mobilization1/01/2008
Start of Production1/01/2008
Start of First Sequence1/01/2008
End of Last Sequence6/01/2008 10:36:00 PM

Completed Production

Costing Report

Total Cost Estimate ($1,188,333)
Total Cost Estimate$1,188,333
Avg Total Cost Per FF Prime Km472.04 km$2,517
Avg Total Cost Per FF Sq Km94.41 sq km$12,587
 
Distance and Area Based Costs - N/A
Production Duration Costs (5d 22:36) $1,188,333
OnlineDurationRateCost
Recording Prime3d 01:42$200,000$614,167
Recording Reshoot3:41$200,000$30,694
Recording DNP1:37$200,000$13,472
Subtotal3d 07:00$658,333
 
OfflineDurationRateCost
Line Change Prime2d 10:14$200,000$485,278
Line Change Reshoot2:41$200,000$22,361
Line Change DNP2:41$200,000$22,361
Subtotal2d 15:36$530,000
 
Shot Based Costs - N/A
Mobilization Costs - N/A
Demobilization Costs - N/A

Production Statistics

General
Online Duration3d 07:00
Offline Duration2d 15:36
Overall Duration5d 22:36
 
All Sequences
Total Sequences29
Total Duration3d 07:00
Average Duration2:43
Total Distance564.82 km
Average Distance19.48 km
 
All Line Changes
Total LCs29
Total LC Expected2d 18:16
Total LC Delays-2:40
Total LC Duration2d 15:36
Average LC Duration2:16
Standard Turn Duration2:40
Obstructed LCs0
 
Calibrated Line Changes
Calibrated LC's28
Calibrated LC Duration2:16
Calibrated LC Error0:07
 
Sequence by Type
#AverageTotal
Prime272:443d 01:42
Infill00:000:00
Reshoot13:413:41
DNP11:371:37
 
Line Changes by Type
#AverageTotal
To Prime272:092d 10:14
To Infill00:000:00
To Reshoot12:412:41
To DNP12:412:41